Location
Morgan, UT
Project Duration
1 month (2020)
Project Type
Dry Utilities Excavation and Streetlight Installation
Scope of Work
Excavation for dry utilities and installation of streetlights in a 32-unit, multi-family development
Unique Problem Solved
The challenge with this project was meeting the tight deadline for conduit installation. We had to condense our timeline in order to install the conduit before asphalt paving commenced.