Location

Morgan, UT

Project Duration

1 month (2020)

Project Type

Dry Utilities Excavation and Streetlight Installation

Scope of Work

Excavation for dry utilities and installation of streetlights in a 32-unit, multi-family development

Unique Problem Solved

The challenge with this project was meeting the tight deadline for conduit installation. We had to condense our timeline in order to install the conduit before asphalt paving commenced.