Location
Wrangler Circle, Golden Eagle, Hideout UT
Project Duration
2 Weeks
Project Type
Dry utilities, Applicant Built Line Extension
Scope of Work
1800′ of dry utilities, 16 lot subdivision
Unique Problem Solved
Coordinated with the developer to install crossings correctly and effectively before Rocky Mountain Power provided plans. Installed power long before Rocky Mountain Power would have while saving the developer over 18% compared to a traditional Rocky Mountain Power build.